- HAPPY HOLIDAYS FROM THE JACKSON STREET STORMWATER PROJECT TEAM!
- Construction activity on the new stormwater pipe will be paused beginning Thursday, December 24, 2020, with crews resuming work on Monday, January 4, 2021. Ames Construction, the City’s contractor on the project, will have staff on site during this period, however, to assist National Jewish Health (NJH) with loading dock operations (trash and deliveries).
- Crews will continue storm pipe installation in the south end of the NJH parking lot and under E. 14th Avenue. During this phase of construction, which is expected to be completed in May or June 2021:
- Full lane closures of E. 14th Avenue will be required between Garfield and Harrison Streets to ensure the safety of the construction crews as they install the pipe twenty-two feet below ground.
- The intersections of Garfield and 14th and Harrison and 14th will remain open to through traffic.
- Local vehicular traffic will be maintained in the area, with the exception of the closure at E. 14th Avenue and Jackson Street.
- Sidewalks on the north side of 14th between Garfield and Harrison will be closed, while sidewalks on the south side of 14th will remain open.
- Access to residences and businesses will be maintained during construction.
- In addition to installation of the new stormwater pipe, you may have noticed increased construction activity and traffic signage in the area generally. This is due to multiple, critical public works projects occurring simultaneously, including lead service line replacement as part of Denver Water’s Lead Reduction Program. Please direct questions about the Lead Reduction Program to lead@denverwater.org or contact Denver Water’s customer care at (303) 893-2444.
- Access to NJH has moved back to E. Colfax Avenue from its temporary location off E. 14th Avenue.
- The RTD bus stop at Garfield on the and south side of E. Colfax Avenue is reopened.
- Construction is also underway by NJH on its new Center for Outpatient Health in the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: December 5, 2020
- Crews will be working in the south end of the NJH parking lot on Saturday, December 5 between the hours of 8 a.m. and 5 p.m.
- Crews will be conducting water line work on Jackson Street between E. 13th and E. 14th Avenues on Monday, December 7 between the hours of 9 a.m. and noon. Impacted residents have been notified.
- Crews will continue storm pipe installation in the south end of the National Jewish Health (NJH) parking lot and under E. 14th Avenue. During this phase of construction, which is expected to be completed in May or June 2021:
- Full lane closures of E. 14th Avenue will be required between Garfield and Harrison Streets to ensure the safety of the construction crews as they install the pipe twenty-two feet below ground.
- The intersections of Garfield and 14th and Harrison and 14th will remain open to through traffic.
- Local vehicular traffic will be maintained in the area, with the exception of the closure at E. 14th Avenue and Jackson Street.
- Sidewalks on the north side of 14th between Garfield and Harrison will be closed, while sidewalks on the south side of 14th will remain open.
- Access to residences and businesses will be maintained during construction.
- In addition to installation of the new stormwater pipe, you may have noticed increased construction activity and traffic signage in the area generally. This is due to multiple, critical public works projects occurring simultaneously, including lead service line replacement as part of Denver Water’s Lead Reduction Program. Please direct questions about the Lead Reduction Program to lead@denverwater.org or contact Denver Water’s customer care at (303) 893-2444.
- Access to NJH has moved back to E. Colfax Avenue from its temporary location off E. 14th Avenue.
- The RTD bus stop at Garfield on the and south side of E. Colfax Avenue is reopened.
- Construction is also underway by NJH on its new Center for Outpatient Health in the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: November 23, 2020
- Crews will not be working on Thursday, November 26 or Friday, November 27 in observance of the Thanksgiving holiday.
- Crews will continue storm pipe installation in the south end of the NJH parking lot and under E. 14th Avenue. During this phase of construction, which is expected to be completed in May or June 2021:
- Full lane closures of E. 14th Avenue will be required between Garfield and Harrison Streets to ensure the safety of the construction crews as they install the pipe twenty-two feet below ground.
- The intersections of Garfield and 14th and Harrison and 14th will remain open to through traffic.
- Local vehicular traffic will be maintained in the area, with the exception of the closure at E. 14th Avenue and Jackson Street.
- Sidewalks on the north side of 14th between Garfield and Harrison will be closed, while sidewalks on the south side of 14th will remain open.
- Access to residences and businesses will be maintained during construction.
- In addition to installation of the new stormwater pipe, you may have noticed increased construction activity and traffic signage in the area generally. This is due to multiple, critical public works projects occurring simultaneously, including lead service line replacement as part of Denver Water’s Lead Reduction Program. Please direct questions about the Lead Reduction Program to lead@denverwater.org or contact Denver Water’s customer care at (303) 893-2444.
- The RTD bus stop at Garfield on the and south side of E. Colfax Avenue is expected to reopen late November.
- Construction is also underway by National Jewish Health (NJH) on NJH’s new Center for Outpatient Health in the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: November 9, 2020
- Weather permitting, crews are expected to complete paving operations on E. Colfax Avenue late in the day on November 10 and reopen E. Colfax in both directions.
- Access to National Jewish Health (NJH) is expected to move back to E. Colfax from its temporary location off E. 14th Avenue on November 12.
- Around November 12, crews will begin storm pipe installation in the south end of the NJH parking lot and under E. 14th Avenue. During this phase of construction, which is expected to be completed in May or June 2021:
- Full lane closures of E. 14thAvenue will be required between Garfield and Harrison Streets to ensure the safety of the construction crews as they install the pipe twenty-two feet below ground.
- The intersections of Garfield and 14th and Harrison and 14th will remain open to through traffic.
- Local vehicular traffic will be maintained in the area, with the exception of the closure at E. 14th Avenue and Jackson Street.
- Sidewalks on the north side of 14th between Garfield and Harrison will be closed, while sidewalks on the south side of 14th will remain open.
- Access to residences and businesses will be maintained during construction.
- A digital message board is in place on E. 14th Avenue at High Street to forewarn commuters and encourage eastbound travelers to detour onto Josephine Street north to E. Colfax or E. 17th Avenue. Additional detour signs are in place at E. 11th Avenue and Josephine Street and E. 18th Avenue and York Street directing travelers to alternate routes.
- Until crews complete paving operations on E. Colfax Avenue, the traffic plan remains as follows:
- The westbound lanes of E. Colfax are open and adjusted to provide one eastbound and one westbound lane for traffic.
- The eastbound lanes of E. Colfax Avenue around Jackson Street are closed.
- Vehicles traveling eastbound on E. Colfax Avenue are not permitted to make left turns onto Monroe, Jackson, and Harrison Streets due to safety and traffic congestion concerns but may make a left turn at Madison Street and at the light at Garfield Street.
- Vehicles traveling westbound on E. Colfax Avenue are not permitted to make left turns onto Madison, Monroe, and Garfield Streets due to safety and traffic congestion concerns.
- Access to businesses, parking lots, and sidewalks in the project area will be maintained during construction, with the exception of the sidewalk adjacent to National Jewish Hospital along E. Colfax Avenue.
- The RTD bus stops at Garfield on both the north side and south side of E. Colfax Avenue will remain closed until E. Colfax is reopened on or around November 10.
- Construction is also underway on the NJH’s new Center for Outpatient Health in the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: October 26, 2020
- Crews are expected to complete installation of the new pipe under E. Colfax Avenue at the beginning of November 2020 and reopen E. Colfax in both directions.
- Around November 10, crews will begin storm pipe installation in the south end of the NJH parking lot and under E. 14th Avenue. During this phase of construction, which is expected to be completed in May or June 2021:
- Full lane closures of E. 14th Avenue will be required between Garfield and Harrison Streets to ensure the safety of the construction crews as they install the pipe twenty-two feet below ground.
- The intersections of Garfield and 14th and Harrison and 14th will remain open to through traffic.
- Local vehicular traffic will be maintained in the area, with the exception of the closure at E. 14thAvenue and Jackson Street.
- Sidewalks on the north side of 14th between Garfield and Harrison will be closed, while sidewalks on the south side of 14th will remain open.
- Access to residences and businesses will be maintained during construction.
- On Tuesday, October 27, 2020, a digital message board is scheduled to be placed on E. 14th Avenue west of York Street to forewarn commuters about the upcoming road closure and encourage eastbound travelers to detour onto York Street south to E. 12thAvenue or onto Josephine Street north to E. Colfax Avenue. Additional detour signs will be in place in the project area as well to direct travelers to alternate routes.
- Until crews finish installing the stormwater pipe in the eastbound lanes of E. Colfax Avenue in early November, the traffic plan remains as follows:
- The westbound lanes of E. Colfax are open and adjusted to provide one eastbound and one westbound lane for traffic.
- The eastbound lanes of E. Colfax Avenue around Jackson Street are closed.
- Vehicles traveling eastbound on E. Colfax Avenue are not permitted to make left turns onto Monroe, Jackson, and Harrison Streets due to safety and traffic congestion concerns but may make a left turn at Madison Street and at the light at Garfield Street.
- Vehicles traveling westbound on E. Colfax Avenue are not permitted to make left turns onto Madison, Monroe, and Garfield Streets due to safety and traffic congestion concerns.
- Access to businesses, parking lots, and sidewalks in the project area will be maintained during construction, with the exception of the sidewalk adjacent to National Jewish Hospital along E. Colfax Avenue.
- The RTD bus stops at Garfield on both the north side and south side of E. Colfax Avenue will be closed during this phase of construction.
- Construction is also underway on the NJH’s new Center for Outpatient Health in the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: September 14, 2020
- Crews will be working on Saturday, September 12 between the hours of 8 a.m. and 5 p.m.
- Access to Garfield Street from E. Colfax Avenue will be closed on Tuesday, September 15 between the hours of 8:30 a.m. and 3:30 p.m. while crews work on an abandoned stormwater pipe located at a manhole in E. Colfax. Access to Garfield Street will be maintained at E. 14th Avenue, and parking on Garfield Street should not be impacted.
- Crews will continue installation of the stormwater pipe in the eastbound lanes of E. Colfax Avenue around Jackson Street. During this phase of construction, the traffic plan is as follows:
- The westbound lanes of E. Colfax are open and adjusted to provide one eastbound and one westbound lane for traffic.
- The eastbound lanes of E. Colfax Avenue around Jackson Street are closed.
- Side streets and alleys in the construction area on the south side of E. Colfax Avenue (Garfield, Monroe, and Madison Streets) are open to traffic.
- Vehicles traveling eastbound on E. Colfax Avenue are not permitted to make left turns onto Monroe, Jackson, and Harrison Streets due to safety and traffic congestion concerns but may make a left turn at Madison Street and at the light at Garfield Street.
- Vehicles traveling westbound on E. Colfax Avenue are not permitted to make left turns onto Madison, Monroe, and Garfield Streets due to safety and traffic congestion concerns.
- Access to businesses, parking lots, and sidewalks in the project area will be maintained during construction, with the exception of the sidewalk adjacent to National Jewish Hospital along E. Colfax Avenue.
- The RTD bus stops at Garfield on both the north side and south side of E. Colfax Avenue will be closed during this phase of construction.
- Access to NJH has been temporarily relocated from E. Colfax Avenue to 14thAvenue.
- Construction is also underway on the NJH’s new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: August 24, 2020
- Crews will be conducting waterline work on the National Jewish Health (NJH) campus on Saturday, August 22, 2020 between the hours of 7 a.m. and 4 p.m. No other properties will be impacted, and NJH’s access to water will be maintained during the course of the work.
- Crews will continue installation of the stormwater pipe in the eastbound lanes of E. Colfax Avenue around Jackson Street. During this phase of construction, the traffic plan is as follows:
- The westbound lanes of E. Colfax are open and adjusted to provide one eastbound and one westbound lane for traffic.
- The eastbound lanes of E. Colfax Avenue around Jackson Street are closed.
- Side streets and alleys in the construction area on the south side of E. Colfax Avenue (Garfield, Monroe, and Madison Streets) are open to traffic.
- Vehicles traveling eastbound on E. Colfax Avenue are not permitted to make left turns onto Monroe, Jackson, and Harrison Streets due to safety and traffic congestion concerns but may make a left turn at Madison Street and at the light at Garfield Street.
- Vehicles traveling westbound on E. Colfax Avenue are not permitted to make left turns onto Madison, Monroe, and Garfield Streets due to safety and traffic congestion concerns.
- Access to businesses, parking lots, and sidewalks in the project area will be maintained during construction, with the exception of the sidewalk adjacent to National Jewish Hospital along E. Colfax Avenue.
- The RTD bus stops at Garfield on both the north side and south side of E. Colfax Avenue will be closed during this phase of construction.
- Access to NJH has been temporarily relocated from E. Colfax Avenue to 14thAvenue.
- Construction is also underway on the NJH’s new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: August 3, 2020
- Installation of phase one of the new, expanded stormwater pipe and restoration of the westbound lanes of E. Colfax have been completed.
- The traffic configuration on E. Colfax has been “flipped” for pipe installation to begin in the eastbound lanes of E. Colfax Avenue around Jackson Street. During this phase of construction, the traffic plan is as follows:
- The westbound lanes of E. Colfax have been reopened and adjusted to provide one eastbound and one westbound lane for traffic.
- Access to Jackson Street from E. Colfax Avenue has been reopened.
- The eastbound lanes of E. Colfax Avenue around Jackson Street are closed.
- Side streets and alleys in the construction area on the south side of E. Colfax Avenue (Garfield, Monroe and Madison Streets) will remain open to traffic.
- Vehicles traveling eastbound on E. Colfax Avenue will not be permitted to make left turns onto Monroe, Jackson and Harrison Streets due to safety and traffic congestion concerns but will be permitted to make a left turn at Madison Street and at the light at Garfield Street.
- Vehicles traveling westbound on E. Colfax Avenue in the project area will not be permitted to make left turns from E. Colfax onto Madison, Monroe and Garfield Streets due to safety and traffic congestion concerns.
- Access to businesses, parking lots and sidewalks in the project area will be maintained during construction, with the exception of the sidewalk adjacent to National Jewish Hospital along E. Colfax Avenue.
- The RTD bus stops at Garfield on both the north side and south side of E. Colfax Avenue will be closed during this phase of construction.
- Access to NJH has been temporarily relocated from E. Colfax Avenue to 14thAvenue.
- Construction is also underway on the NJH’s new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: July 27, 2020
- Installation of the stormwater pipe in the westbound lanes of E. Colfax has been completed. Weather permitting, crews are scheduled to complete paving and striping operations by mid-week. During this work, the westbound lanes of E. Colfax Avenue around Jackson Street will remain closed. The eastbound lanes of E. Colfax Avenue will remain open and adjusted to provide one eastbound and one westbound lane for traffic.
- Weather permitting, beginning on Thursday, July 30, the traffic plan on E. Colfax will “flip” for pipe installation to begin in the eastbound lanes of E. Colfax Avenue around Jackson Street. During this phase of construction, the traffic plan will be as follows:
- The westbound lanes of E. Colfax will be reopened and adjusted to provide one eastbound and one westbound lane for traffic.
- Access to Jackson Street from E. Colfax Avenue will reopen.
- The eastbound lanes of E. Colfax Avenue around Jackson Street will be closed.
- Side streets and alleys in the construction area on the south side of E. Colfax Avenue (Garfield, Monroe and Madison Streets) will remain open to traffic.
- Vehicles traveling eastbound on E. Colfax Avenue will not be permitted to make left turns onto Madison, Monroe, Jackson and Harrison Streets due to safety and traffic congestion concerns but will be permitted to make a left turn at the light at Garfield Street.
- Vehicles traveling westbound on E. Colfax Avenue in the project area will not be permitted to make left turns from E. Colfax onto Madison, Monroe and Garfield Streets due to safety and traffic congestion concerns.
- Access to businesses, parking lots and sidewalks in the project area will be maintained during construction, with the exception of the sidewalk adjacent to National Jewish Hospital along E. Colfax Avenue.
- The RTD bus stops at Garfield on both the north side and south side of E. Colfax Avenue will be closed during this phase of construction.
- Access to NJH has been temporarily relocated from E. Colfax Avenue to 14thAvenue.
- Construction is also underway on the NJH’s new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: July 20, 2020
- Please note that despite the construction at Colfax and Jackson Street, area businesses including Tough Mudder Bootcamp, Bishops Haircuts, Cricket Wireless and Chick-fil-A are accessible both by car and by foot. The combination of the pandemic and construction in the area makes it more important than ever to consider supporting local businesses.
- Due to a variety of unforeseen events including heavy storms and the impacts of COVID-19, construction will continue in the westbound lanes of E. Colfax Avenue until early August. Adjustments to the timeline are reflected in the Project Background section, below.
- Water lines in the project area were temporarily moved early in the construction process to provide construction access. Restoration of water lines for businesses located on the north side of E. Colfax Avenue between Jackson and Harrison Streets and residences on Jackson Street between E. Colfax and 16th Avenues will occur on Sunday, July 19 between the hours of 6:00 p.m. and midnight. Impacted residences and businesses have been notified individually.
- The existing traffic plan will remain in place into August 2020 as follows:
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed.The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood.
- The sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street is closed.
- Access to NJH has been temporarily relocated from E. Colfax Avenue to 14thAvenue.
- Construction is also underway on the NJH’s new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: June 29, 2020
- Please note that despite the construction at Colfax and Jackson Street, businesses including Tough Mudder Bootcamp, Bishops Haircuts, Cricket Wireless and Chick-fil-A are accessible both by car and by foot. The combination of the pandemic and construction in the area makes it more important than ever to consider supporting local businesses.
- Due to a variety of unforeseen events including heavy storms and the impacts of COVID-19, construction will continue in the westbound lanes of E. Colfax Avenue until early August. The resulting adjustments to the construction timeline are at the bottom of this project web page.
- Crews will be working on Saturday, June 27 between the hours of 8 a.m. and 5 p.m.
- Water lines in the project area were temporarily moved early in the construction process to provide construction access.
Restoration of water line locations for businesses and residences in the project area will occur in the coming weeks. Impacted property owners will be notified directly once the schedule is finalized.
- The existing traffic plan will remain in place into August 2020 as follows:
- Intermittent closures of the far right lane of southbound Colorado Boulevard will occur between E. 16th and E. Colfax Avenues to accommodate truck staging for hauling material from the construction site.
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed. The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound. Businesses in the project area are open during construction.
- The sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street is closed.
- Access to NJH has been temporarily relocated from E. Colfax Avenue to 14th Avenue.
- Construction is also underway on the NJH’s new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visithttps://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: June 22, 2020
- Please note that despite the construction at Colfax and Jackson Street, area businesses including Tough Mudder Bootcamp, Bishops Haircuts, Cricket Wireless and Chick-fil-A are accessible both by car and by foot. The combination of the pandemic and construction in the area makes it more important than ever to consider supporting local businesses.
- Due to a variety of unforeseen events including heavy storms and the impacts of COVID-19, construction will continue in the westbound lanes of E. Colfax Avenue until early August. Adjustments to the timeline are reflected in the Project Background section, below.
- Water lines in the project area were temporarily moved early in the construction process to provide construction access. Water lines were successfully restored at Chick-fil-A and National Jewish Health (NJH) last week. Restoration of water line locations for other businesses and residences in the project area will occur in the coming weeks. Impacted property owners will be notified directly once the schedule is finalized.
- The existing traffic plan will remain in place into August 2020 as follows:
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed.The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood.
- The sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street is closed.
- Access to NJH has been temporarily relocated from E. Colfax Avenue to 14thAvenue.
- Construction is also underway on the NJH’s new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: May 18, 2020
- Please note that despite the construction near businesses at Colfax and Jackson Street, these businesses are accessible both by car and by foot. The combination of the pandemic and construction in the area makes it more important than ever to consider supporting local businesses.
- Water lines in the project area were temporarily moved early in the construction process to provide construction access. Crews will be onsite to restore the original fire line connection for Chick-fil-A on Sunday, May 17 between the hours of 8 a.m. and 5 p.m. Restoration of water line locations for other businesses and residences in the project area will occur in the coming weeks. Impacted property owners will be notified directly once the schedule is finalized.
- The existing traffic plan will remain in place through May and into late June as follows:
- Intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood.
- During the first phase of construction, the sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street will be closed.
- Access to National Jewish Health has been temporarily relocated from E. Colfax Avenue to 14th Avenue.
- Construction is also underway on the National Jewish Health new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week Ahead: May 11, 2020
- Crews will be working on Saturday, May 9 between the hours of 8 a.m. and 5 p.m.
- The existing traffic plan will remain in place through May and into late June as follows:
- Intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood. Businesses in the project area are open during construction.
- During the first phase of construction, the sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street will be closed.
- Access to National Jewish Health has been temporarily relocated from E. Colfax Avenue to 14th Avenue.
- Construction is also underway on the National Jewish Health new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.*Because of state and local stay-at-home orders, our direct, face-to-face communication with the community is limited. If you think this construction information would be helpful to your neighbors, please forward this email to them and suggest they sign-up to receive future updates at ccd.constructionupdates@gmail.com. Thank you!
- Crews will be working on Saturday, April 25 between the hours of 8 a.m. and 5 p.m.
- The existing traffic plan will remain in place through April and into late May as follows:
- Intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood. Businesses in the project area are open during construction.
- During the first phase of construction, the sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street will be closed.
- Access to National Jewish Health has been temporarily relocated from E. Colfax Avenue to 14th Avenue.
- Construction is also underway on the National Jewish Health new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.*Because of state and local stay-at-home orders, our direct, face-to-face communication with the community is limited. If you think this construction information would be helpful to your neighbors, please forward this email to them and suggest they sign-up to receive future updates at ccd.constructionupdates@gmail.com. Thank you!
The Week Ahead: March 30, 2020
- Crews will be working on Saturday, March 28 and April 4 between the hours of 8 a.m. and 5 p.m.
- The existing traffic plan will remain in place as follows:
- Intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison
Street for access to local businesses and the neighborhood. Businesses in the project area are open during construction.
- During the first phase of construction, the sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street will be closed.
- Access to National Jewish Health has been temporarily relocated from E. Colfax Avenue to 14th Avenue.
- Construction is also underway on the National Jewish Health new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week & Weekend Ahead: March 16, 2020
- The existing traffic plan will remain in place as follows:
- Intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood. Businesses in the project area are open during construction.
- During the first phase of construction, the sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street will be closed.
- Access to National Jewish Health has been temporarily relocated from E. Colfax Avenue to 14th Avenue.
- Construction is also underway on the National Jewish Health new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week & Weekend Ahead: March 2, 2020
- In the coming weeks, intermittent closures of the far right lane of southbound Colorado Boulevard between E. 16th and E. Colfax Avenues will occur to accommodate truck staging for hauling material from the construction site.
- The westbound lanes of E. Colfax Avenue around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax Avenue will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on E. Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood. Businesses in the project area are open during construction.
- During the first phase of construction, the sidewalk on the north side of E. Colfax Avenue around the intersection at Jackson Street will be closed.
- Access to National Jewish Health has been temporarily relocated from E. Colfax Avenue to 14th Avenue.
- Construction is also underway on the National Jewish Health new Center for Outpatient Health on the northwestern most section of the former patient parking lot, situated at E. Colfax Avenue, between Jackson and Garfield Streets. For more information about this project, please visit https://nationaljewish.org/center-for-outpatient-health/overview.
The Week & Weekend Ahead: February 18, 2020
- Ames Construction will be installing two conduits across E. Colfax Avenue, which will require temporary, full lane closures across Colfax around Jackson Street. To minimize disruption to residents, businesses and commuters, current plans are to perform the work between 10 p.m. Saturday, February 22 and 5 a.m. Sunday, February 23.
- Crews conducted work on water lines beginning at 10:30 p.m. on Saturday, February 8. Work was completed earlier than anticipated, with water fully restored to residents and businesses by 5 a.m. on Sunday, February 9. Thank you for your patience and understanding while crews performed this critical work.
- The westbound lanes of E. Colfax around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax will remain open (with the exception of the conduit installation on February 22-23, mentioned above) and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood. Businesses in the project area are open during construction.
- During the first phase of construction, the sidewalk on the north side of E. Colfax around the intersection at Jackson Street will be closed.
- The lane closures on E. Colfax necessitated temporarily moving the entrance to National Jewish Health (NJH) to 14th Avenue. Signage has been added to help patients find that entrance. Additionally, pedestrian access to NJH is currently located on 14th Avenue.
The Week Ahead: February 3, 2020
- The westbound lanes of E. Colfax around Jackson Street will remain closed during the first phase of construction. The eastbound lanes of E. Colfax will remain open and adjusted during this time to provide one eastbound and one westbound lane for traffic.
- Please note that vehicles traveling westbound on Colfax Avenue are able to turn right on northbound Harrison Street for access to local businesses and the neighborhood. Businesses in the project area are open during construction.
- During the first phase of construction, the sidewalk on the north side of E. Colfax around the intersection at Jackson Street will be closed.
- To minimize disruption to businesses and residences in the immediate project area, Ames Construction, the City’s contractor for this project, will be working on water lines from 10:00 p.m. on Saturday, February 8 until 9:00 a.m. on Sunday, February 9. Impacted residences and businesses will be notified individually.
- To minimize the impact on parking availability in the surrounding neighborhoods, Ames has secured off-street parking for its project team and work crews.
- The lane closures on E. Colfax necessitated temporarily moving the entrance to National Jewish Health (NJH) to 14th Avenue. Signage has been added to help patients find that entrance. Additionally, pedestrian access to NJH is currently located on 14th Avenue.
Businesses in the project area are open during construction. Please shop or visit to support them during this project!
Project Background
The Jackson Street Storm Drain Project will begin on the north side of E. Colfax Avenue at Jackson Street. Work will proceed south across E. Colfax, through the existing City right-of-way (ROW) in the National Jewish Health (NJH) parking lot and continue on E. 14th Avenue at Jackson Street for ½ block east towards Harrison Street. The entire project will take approximately 18 months.
Overview of Construction Timeline & Traffic Impacts
Construction in westbound lanes of E. Colfax Avenue at Jackson Street
- During this phase of construction, the westbound lanes of E. Colfax Avenue around Jackson Street will be closed, while the eastbound lanes of E. Colfax will remain open and adjusted to provide one eastbound and one westbound lane for traffic.
- Access to Jackson Street from E. Colfax will not be open to vehicles during work in westbound lanes of E. Colfax.
- The westbound lanes of E. Colfax will be reopened and adjusted to provide one lane of traffic in each direction.
- Access to Jackson Street from E. Colfax will reopen.
- The traffic plan on E. Colfax will “flip” for pipe installation to begin in the eastbound lanes of E. Colfax Avenue around Jackson Street and the eastbound lanes will be closed.
Mid-August 2020 – March 2021 (7-8 months)
South end of Jackson ROW/NJH parking lot (Circle Entrance into E. 14th Avenue) and E. 14th Avenue
- Full lane closures will be required on E. 14th Avenue in the area around Garfield, Jackson and Harrison Streets during the final phase of the project to ensure the safety of the construction crews as they install the new pipe.
- Detours will be put in place during this phase of construction.
General Construction Impacts
Utilities: There may be temporary interruptions of utility services during construction. Advance notice will be provided to impacted residents.
For questions or to sign up for weekly updates, email us at ccd.constructionupdates@gmail.com.
For urgent, construction-related questions, call Gary Padilla, on-site inspector at 303 446-3445 or Perry Lopez, contractor at 303 995-2278.
For non-urgent questions that will be answered within a few hours during regular business hours, call 720 460-9055.
Learn more at: denvergov.org and enter “Jackson Street Storm” in the search bar.
The post Jackson Street Storm Drain Updates appeared first on Cranmer Park/Hilltop Civic Association.
https://www.newsbreak.com/topics/guerin-green/?=DenverNews
No comments:
Post a Comment